Tonight the district hosted a second neighborhood informational meeting at McMinnville High School to outline plans for the upcoming construction projects at the high school.
Representatives from the school district, the architect and general contractors shared the scope and schedule of the planned reconstruction and renovation of McMinnville High School, including
Phase one – Career Technical Center, parking, bus lane, cafeteria, entry security
February 2017 – August 2017
Phase two – Baker Field, repair and renovation
May 2017 – August 2017
Phase three – Repair and renovation
May 2018 – August 2018
Phase four – High school addition demolition and construction
June 2018 – August 2019
- Building design presented by Marc Nordean, DOWA
- Construction logistics presented by Kurt Schwabauer and Lee Zumwalt, LCG Pence
- Community contracting efforts presented by Dave Hays, LCG Pence
Click here to see the site plans that were presented at the meeting.
21 September, 2016